"It's getting bad again," commercial fisherman Rob Burcaw told Sea Isle City's council about Townsend's Inlet, as OCNJ Daily reported on October 13. His family runs a commercial fishing and lobster operation in Sea Isle, and he described captains taking extra care steering big boats under the bridge while sand shifts in the channel.
From Avalon's side of the bridge, that problem and the new beach between the inlet and 27th Street are the same story. The dredge "Delaware" spent September and October pumping sand from a Townsend's Inlet borrow area onto Avalon's north end. This week the same equipment is supposed to take on the inlet sandbar, and that sand will also end up on Avalon's beach. Avalon's north end is finishing October with a beach built from the inlet. On Saturday, October 24, volunteers will plant dune grass through the borough's twice-yearly planting.
A Million Cubic Yards, Logged Day by Day
The borough has kept a running log of the Avalon beach fill project on its website, often with a daily total. On October 1, the log said the project called for more than 900,000 cubic yards. By October 14, the total had passed that.
| Borough update | Total sand placed (cubic yards) | Beach paths closed that day |
|---|---|---|
| September 16 | 415,718 | 10th to 12th streets |
| September 20 | 539,951 | 14th to 16th streets |
| September 29 | 578,886 | 14th to 16th, plus 18th to 23rd for storm erosion |
| October 1 | 646,672 | 15th to 17th, plus 18th to 23rd |
| October 9 | 929,724 | 19th to 23rd, plus 12th Street for a subcontractor |
| October 14 | 1,007,912 | 20th to 27th streets |
The closures in the right-hand column moved south block by block. By September 20, the borough reported that every beach north of 14th Street had been filled, and the work was heading toward 25th Street. The Norfolk Dredging operation ran 24 hours a day, seven days a week, and stopped only for mechanical failure or bad weather.
The October 14 entry is the latest in the log. It said the Delaware was expected to finish the beach fill that week. The safest way to know whether a particular path between 20th and 27th streets has reopened is the borough's update page.
The Nor'easter That Pushed Back the Finish
The schedule changed in late September. On September 20, the borough reported that work had been suspended at 6 a.m. that Sunday because rough seas were expected from northeasterly winds. The dredge went to safe harbor in Great Egg Harbor, and the U.S. Army Corps of Engineers planned to survey again before work resumed.
After that weekend storm, the borough's Department of Public Works closed paths from 18th to 21st streets because of significant erosion. It also temporarily closed 22nd through 26th until crews could make them safe. Paths from 24th to 26th reopened first. Work resumed on September 28 at 6 p.m., and the 18th-to-23rd closures stayed in the log for days afterward, now tied to the erosion rather than to construction.
The storm also enlarged the job. In its October 14 update, the borough said the Army Corps had added 100,000 cubic yards to the project, concentrated on the north end where sand was lost in the late September nor'easter. On October 1, the borough had estimated the Avalon fill would finish on or about October 12. The work was still underway on October 14, with the added sand still to come.
The Avalon Environmental Commission has long noted that storms hit the dunes in northern Avalon especially hard. This fall's storm landed on the same stretch where the new sand was going.
The Same Pipe Takes On a Second Job
The inlet work exists because the dredge was already in place. On October 15, Avalon announced it had signed an agreement with Norfolk Dredging Company to remove up to 135,800 cubic yards of material from the Townsend's Inlet navigation channel. That sand will go on the north-end beachfront for storm protection. The borough said the project needed a seven-party agreement, along with permits from the Army Corps and the New Jersey Department of Environmental Protection.
According to OCNJ Daily's account, the sandbar started forming last spring in the channel under the Townsends Inlet Bridge. The Sea Isle and Avalon agreement calls it an "imminent threat" to commercial, charter and recreational boats. Sea Isle Mayor Leonard Desiderio put the cost at about $1.6 million and said it "would be substantially more if we didn't do it now," because the dredge pipe and equipment were already on site. The outlet reported this split of the $1.6 million:
- Borough of Avalon: $650,000
- Sea Isle City: $650,000
- Cape May County: $250,000
- Cape May County Bridge Commission: $50,000
There's a reason so many parties are paying. Avalon's announcement says no single entity is responsible for routine dredging of the channel. OCNJ Daily reported that Townsends Inlet is not a designated federal navigation channel, and that Congressman Jeff Van Drew hopes to have it studied as one so it would have a permanent source of funding. Meanwhile, the Coast Guard has placed buoys to guide boaters through the channel and under the bridge. Avalon puts the inlet's economic activity at $15 million to $21 million a year.
The two towns describe the cut differently. Avalon's announcement says it will be 150 feet wide. Desiderio, as quoted by OCNJ Daily, described a section 200 feet wide and 20 feet deep. The Cape May County Herald reported on October 16 that the work was set to start October 20. Sea Isle Business Administrator George Savastano told council the job should take about three days. That projection puts completion close to this week, though the late September storm already showed how weather can change a dredge schedule.
This has happened before. Charter owner Bob Rush of Starfish Boats told council the inlet was dredged in 1992 or 1993 during a similar buildup, according to OCNJ Daily. The same report says a sandbar formed five years ago and then disappeared on its own. The Bridge Commission has said the fast, deep water at the bridge creates a whirlpool effect that changes the nearby beach.
Saturday, October 24, on the Beach
Dredges move sand, but planted grass is what holds a dune together, and Avalon's Fall Dune Grass Planting falls right as the heavy equipment finishes. The Environmental Commission runs the planting twice a year with volunteers. The borough's October 8 announcement invites groups and families and sends registration through the Department of Recreation. The 2026 notice doesn't say which blocks will be planted.
The same Saturday has more going on along the same stretch of town:
- 8:30 a.m. Fall Dune Grass Planting volunteers meet at Avalon Community Hall, 3001 Avalon Ave., for a short planting demonstration, then head to the beach. The Seven Mile Times listing runs it to 10:30 a.m., with October 25 as the rain date.
- 9 a.m. to 12:30 p.m. Clean Ocean Action's Fall Beach Sweep, held with the boroughs of Avalon and Stone Harbor, starts at the 30th Street Boardwalk. Volunteers should bring gloves and dress for the weather. Trash bags and pickers are provided.
- 5 to 7 p.m. Avalon Recreation's Trunk-or-Treat takes place in the parking lot at 30th Street and Avalon Avenue.
Borough-wide trick-or-treat in Avalon and Stone Harbor follows on Saturday, October 31, from 5 to 8 p.m. The September updates also bear repeating for anyone walking the new sand. The borough reported that lifeguards are off duty for the season and told the public not to swim in the ocean.
What Sits Behind the Closed Paths
Several of the places still open this fall sit on the blocks the dredge just worked. The Avalon Chamber's restaurant-hours page lists Circle Tavern at 2008 Dune Drive, open Thursday through Sunday from 11 a.m. to 10 p.m. It lists Café Loren at 2288 Dune Drive, open Friday through Sunday from 5:30 to 9 p.m., and The Whitebrier at 260 20th St., open daily from 4 to 10 p.m. The Diving Horse at 2109 Dune Drive is open Thursday through Sunday from 5 to 10 p.m. It closes for the season after October 30. The Chamber page has no update date, so call ahead before you go.
On November 11 at 11 a.m., Avalon's Veterans Day Ceremony takes place at Veterans Plaza, 21st Street and Dune Drive, a block from the paths that were closed through mid-October. An open house follows at Stephen C. Ludlam Post 331.
The north end's next project is a park. Avalon Council has received plans for Grace O'Brien Park at 8th Street and Ocean Drive, with accessible playground equipment, more green space and four bocce courts. The borough plans to apply for county open-space funding and expects construction in the first quarter of 2027.
The Chamber has already set the dates for Thanksgiving weekend. Festive Friday, November 27, runs from 11 a.m. to 4 p.m. in the shopping district and ends with a 5 p.m. tree lighting with Santa and Mayor John McCorristin. Snowfest Saturday follows on November 28. The Turkey Trot 5K starts at 10 a.m. that Friday. The Chamber's page lists the start at 30th Street and Avalon Avenue, while Avalon Recreation lists Community Hall, so check with the organizer before race morning.
Greg Davis spent more than 20 years in construction and environmental consulting before real estate, and he follows projects like this one closely. If you own in Avalon and want a straight read on how this fall's work affects your property or your plans, Greg Davis Luxury Homes is glad to help. Schedule a consultation.